To ensure a successful inspection and smooth progress of your project, the following requirements must be met before scheduling an underground trench inspection. Failure to meet any of these standards may result in delays and additional costs.
Pre-Installation Requirements
You must Call Before You Dig (811) – it is the customer’s responsibility to comply with local dig notification regulations. All utility locates must be completed and visible.
Trench must be within the previously flagged or staked right-of-way. Survey staking may be required for verification.
Excavated material (spoils) must be placed at least 2 feet away from the trench and transformer locations.
You must schedule a trench and conduit inspection with UEC 24 hours before backfill.
United Electric provides and installs all meters. United Electric will install current transformers and metering for services exceeding 400 amperes single phase and 200 amperes for three phase.
Location:
Must be installed 5 to 6 ft. from the finished grade to the center of the meter socket. Meter base and conduit must be placed on the outside wall or pole. There shall be a minimum of 3 feet of un-obstructed space in front of the meter.
The preferred meter base location is on the transformer or splice box side of the house/ building. Meters must also be protected from physical damage. A post mounted meter or manufactured home pedestal shall be located facing the road for meter access.
Meter equipment attached to member owned equipment shall be a minimum of 6’ from United Electric owned equipment.
Irrigation pump meters shall be installed so that the meter is not sprayed by sprinklers or chemicals.
Metering equipment will not be installed in a manner that limits the access or causes damage to the meter. It is the member’s responsibility to provide and maintain adequate work space and clearances, obstructions including shrubbery and landscaping must be kept clear from the meter location.
Meter Installations:
All installations must conform to the National Electric Code and United Electric Co-op, Inc. Service Requirements. Meter base must be plumb and level and securely mounted to a rigid surface. All conductors must be securely fastened and must not interfere with the meter.
Wiring should be in accordance with United Electric’s wiring diagram and color codes.
The meter shall be installed on the supply side of the service equipment.
Meter base must be readily accessible, free from vibration, corrosive atmosphere and abnormal temperatures. If a meter is required to be made accessible for any reason, the member must, at their expense, move the meter socket to an accessible location.
When two or more meters are installed at a building, each meter mounting shall be permanently and legibly marked to indicate the service being metered.
United Electric meter seals shall not be broken without authorization.
Ownership of equipment
The member owns all metering equipment except for the meter and instrument transformers.